Operating Instructions for Rope Pull Switches
RPS...

Installation sequence

Installation must be performed only by authorized personnel.

1 A

1.1A

1.2A

1.3A

Attach bearing element with tensioner spring; fit pull rope: sheathing must be removed in clamping area; insert rope
in the fast-action clamping head as shown and secure.

B

1.1B

1.2B

Attach bearing element with counterspring; fit pull rope: secure rope as shown with thimble and rope clamp, attach
rope bridge to limit travel of counterspring with thimbles and rope clamps.

2

2 - 5 m

La = 150 mm

rope tension

Observe distance to the 1st support point. The 1st rope support next to the switch must be installed after La =150
mm.
Install supports at intervals of 2 – 5 m.

3

Fasten the RPS switch with four M5 screws
(also M6 for RPS-M) .

Maximum tightening torque M = 2 Nm.

The emergency stop switches must be
positioned so that the rope or emergency stop
slam button can be reached without obstacles
in hazardous situations.