Final configuration and training, B1.0 final functional checks and configuratioin – MTS Criterion 40 - Installation and Commissioning Plan User Manual
Page 11
Advertising

Installation and Commissioning Plan
MTS Criterion
TM
Series 40
11
FINAL CONFIGURATION and TRAINING
B1.0 FINAL FUNCTIONAL CHECKS AND CONFIGURATIOIN
Item Description
Performed
On Site
B1.1
Create backup of all critical files.
B1.2
Create up to three basic methods according to user-
defined specifications. Basic methods are created from a
standard compression, tensile, or peel method template.
Refer to section A1.5 for definitions of method
modifications.
B1.3
Verify that test methods are working and the results are
acceptable / calculated correctly.
B1.4
Clean up/organize the system workspace. Tie-wrap loose
cables, close machine panels, and so forth.
B1.5 For computers purchased through MTS, complete the
warranty registration.
Advertising