Installation and Commissioning Plan


MTS Criterion

TM

Series 40

5

•

Computer modifications. Will any other computer software or hardware,

such as network adapters or LIMS software, be added to the system? Please

provide information about any possible computer modifications prior to the

installation. If time permits in the later stages of the installation, the FSE will

assist your Information Services Technician with the integration of

peripherals and network capabilities. The FSE is not trained in information

systems troubleshooting techniques and is not responsible for compatibility

issues regarding the integration of devices other than those required for

communication with the MTS-supplied controller. MTS understands that

networking can play a vital role in your testing needs. MTS equipment and

software is designed to help you successfully achieve this need. However,

MTS respectfully requests that you do not modify the computer by

reconfiguring the PC factory settings or the configuration of an MTS-

supplied computer until the FSE has arrived on-site. This request extends to

peripherals as well as network hardware.

•

If the PC is customer supplied, the customer IT Dept must provide

Administrator access for the FSE to install and configure the testing software

on the PC properly. This must be arraigned before the FSE arrives on site.

•

Date and time of installation. Confirm with the FSE the exact date and time

for performing the installation, including the time for uninterrupted training.

•

Visitor information. Please provide any visitor restrictions such as security

clearance, safety requirements, or working hours. The FSE requires at least

eight full working hours each day with an additional hour for lunch.