Installation and Commissioning Plan


6

MTS Criterion

TM

Series 40

Important

•

Please expect at least eight full hours of training time. The objectives for the

eight hours of training time are listed under A4.0 and B2.0 of this document.

The training sessions have been divided into two four-hour sessions to

minimize the impact on your daily business activities and to improve the

material retention level for the trainees. If these objectives are met before the

end of eight hours, the remaining training agenda may be discussed with the

FSE. The exception to this is when one day of installation and training is

purchased.

•

Please ensure that your staff will be available for at least eight full hours of

uninterrupted training. The timing of this should be established in advance

with the FSE. The uninterrupted basis is very important. Interruptions can

seriously compromise the effectiveness of the training and therefore,

compromise your ability to use the system correctly and fully.

•

If the installation site is not ready at the time of the scheduled installation, the

installation will be rescheduled. Lost time due to the site not being ready is

not included in the contract price.