Decommissioning – MTS Acumen Electrodynamic Test System Load Frame User Guide User Manual

Page 68

Advertising
background image

Decommissioning

The decommissioning process is performed when the system is going to be moved or taken out of service.
Disassembly is required when performing either of these tasks.

To decommission the system:

1. Remove the specimen and fixtures. Large grips should be removed if the load frame could be tipped over.

2. Isolate the system from electrical power.

3. When the system electronics, control software, and the system PC are powered down, turn off the system’s

main electrical supply and disconnect all cables.

4. Disconnect all cables from the controller.

5. Cover the material testing machine with a dust cover, such as plastic foil. Allow for sufficient ventilation

or place a dehumidifier near the equipment.

6. Place the accessories and the instruction manual in a clean, dust-protected place, such as a tool cabinet.

Caution:

Electrical components and parts can contain hazardous chemicals and compounds.

Always refer to local codes that govern the disposal of potentially hazardous materials and
follow these codes for the proper handling and disposal of these materials.

You should follow internal safety policies for safe disposal of parts of the machine. Refer to
the MSDS for oils and greases that are used on the machine.

68 MTS Acumen™ Electrodynamic Test System

Decommissioning

Advertising