Load Unit installation consists of these four major tasks —

Inspect for Shipping Damage

Unpack and Move the Platen

Install the Crosshead Assembly

Make Connections, Bleed Lifts, Tighten Columns

Special equipment needed —

An overhead crane and lifting slings or chains capable of lifting the load unit

Torque wrenches:

322.21 – 700 lbf·ft (950 N·m) capacity
322.31 – 1400 lbf·ft (1900 N·m) capacity
322.41 – 1400 lbf·ft (1900 N·m) capacity

Molykote G-n paste

Inspect for Shipping Damage

Look for the following:

Scratches in the load unit or lift cylinder columns

Damaged electrical connections

Damaged hydraulic connections

Dents and other structural damage

Torn, kinked, or breaking hoses

Report any damage found to both the carrier and MTS. In the U.S. and Canada,
call the MTS HELPLine at 1-800-328-2255. Elsewhere, contact your local MTS
office.

Load Unit

Standard Dimension Platen

Weight

322.21

28 X 40 in

711 X 1016 mm

3000 lb

1370 kg

322.31

34 X 40 in

864 X 1016 mm

4500 lb

2050 kg

322.41

42 X 60 in

1067 X 1524 mm

8500 lb

3870 kg