Front access – bottom incoming cables, Figure 11 – Rockwell Automation 1512A MV Controllers, 400A One-High Cabinet, Standard and Arc-Resistant Enclosure User Manual
Page 18

10
Rockwell Automation Publication 1512A-UM100F-EN-P - May 2013
Chapter 2
Installation – Standard Enclosure
10. Reverse procedure after cables have been installed.
Figure 11 - Power Bus with Barrier Removed
Front Access – Bottom Incoming Cables
If the incoming cables in your cabinet enter the section from the bottom, follow
the same procedure as for
Front Access – Top Incoming Line Cables
.
1. Open the power cell door.
2. Locate incoming cable duct at rear left-hand side of power cell (see
).
3. Remove self-tapping screws from the cable duct access barriers. Remove
barriers.
4. Route and install incoming line cables to power bus. Torque to
specifications (refer to
Recommended Torque Values on page 2 of
).
5. Reverse procedure after cables have been installed.
ATTENTION: Ensure all barriers are replaced before re-energizing the
equipment. Failure to do so may result in electrical faults and cause damage to
equipment or severe injury to personnel.
TIP
Access to incoming cable duct in the power cell is also required.
Low Voltage Panel
Power Bus