7. Install incoming line cables to power bus. Torque to specifications (refer
Recommended Torque Values on page 2 of Chapter 1
8. Reverse procedure after cables have been installed.
Figure 29 - Power Bus with Bottom Access Barrier Removed
Front Access – Top Incoming Cables (Top Entry/Exit)
Top entry one high ArcShield units are 0.9 m (36 in.) wide versus bottom entry
units which are 0.7 m (26 in.) wide.
1. Complete the Power Lock-out Procedure (refer to
Procedure on page 41 of Chapter 5
) for both the medium voltage and the
power bus.
2. Open the top medium voltage cell door (refer to
).
3. Open the bottom empty cell door (refer to
4. Remove retaining screws from removable bus access barriers to expose
incoming cable connection to main bus (