3 - commissioning, Introduction, Chapter 3 – Rockwell Automation 6000 PowerFlex Medium Voltage Variable Frequency Drive Commissioning Manual User Manual
Page 31: Commissioning, Chapter

Rockwell Automation Publication 6000-IN007A-EN-P - October 2014
31
Chapter
3
Commissioning
Introduction
A number of activities are required before the Control System Check can be
performed.
The complete Control System Check requires the following procedures to be
performed.
ATTENTION: The Control System Check requires LV Control power only. The
Input Circuit Breaker must remain locked out and tagged out for this procedure.
Procedure
Page
Simulate Closed Input Circuit Breaker
Procedure
Page
Verify Factory Default Settings
Set P Parameters to Enable Testing
Verify Operation of Frequency Steps
Verify Operation to Set Frequency
Verify Switching from Local Control to Remote Control
Verify Operation of Input/Output and Bypass Isolation Switches (Manual Bypass)
(1)
(1) Only required if a bypass configuration is supplied.
Verify Operation of Input/Output and Bypass Contactors (Automatic Bypass)
(1)