Install Welded Parts

Front Page

Part Lists

Great Plains Manufacturing, Inc.

7

02/21/2012

Front Page

Part Lists

166-367M

Install Pivot Tubes

Start with the right side of the implement.

Refer to Figure 10, Figure 11and Figure 12
38. Remove paint from the frame around the former

bearing mount holes.

39. Select one new:

266-295D CONTACT WHL PVT TUBE

Insert the tube through the frame holes where the
previous pivot shaft was removed.

40. Adjust the tube position for a reveal of 81.0 mm

(3.10 in) on the outside of the frame (left reveal on
left side; right reveal on right side). Tack weld the
tube. Recheck the reveal.

41. At the outside face of the outside frame plate, and

the inside face of the inside frame plate, weld the
contact circumference of the tube/frame joints with a
9 mm (

3

8

in) weld fillet

.

Note: It is not necessary to fill the former bolt holes

during welding.

42. Repeat step 38 through step 41 for the left side.

43. Wait for the welds to cool.

44. At all welds, remove welding residue and any

charred paint. Apply matching green paint.

45. Allow paint to dry.

Figure 10

Pivot Tube and Bearings

29379

14

12

12

15

18

16

14

4

.epsi

100%

Figure 11

Pivot Tube Placement

32067

(3.19 in)

81.0 mm

14

4

Figure 12

Pivot Tube Weld

32067

14

5

6