Leveling Boom
Boom sections must be level across the span for even noz-
zle height during spraying.
To adjust an inner-arm section, fold boom and loosen bolts
(1) holding shims (2). Add or remove shims as necessary.
Figure 2-1
Shimming Inner Wing
To expose shims for outer-arm section, fold boom and
band inner and outer arms together. Disconnect cable
from spring shackle and unfold wings while still banded to-
gether. Add or remove shims (1) by loosening the bolt (2)
shown in Figure 2-2.
Figure 2-2
Shimming Outer Wing
NOTE: Boom arms are disassembled in Figure 2-1 and
Figure 2-2 for illustration purposes only.
16916
16917
Section 2
Preparation and Setup
Locking System
The CF500 and CF600 have a locking system that auto-
matically locks the wing sections during folding and trans-
port. For proper folding, the boom-lock cable must be tight
enough that the lock arms (1) just clear their stops when
unfolded (2) and rest secure against the stop when folded
(3).
Figure 2-3
Lock Arms
To adjust the tension on the boom-lock cable, loosen jam
nut and turn clevis. See Figure 2-4.
Figure 2-4
Adjust Boom-Lock Cable
Install Boom Nozzles and Tubing
Wet Boom Option
1.
Prepare for installation.
Sort tubing sections by color ties. Use four sections
with yellow ties for the center section. Use two sec-
tions with red ties for the left wing. Use two sections
with green ties for the right wing.