2015 Three-Point Soybean Machine 173-088M
b.
Slide the 7/8” hex shaft back through the bear-
ing mounted on the drill frame (#3). The shaft is
trapped in place by driving roll pins (#4) on ei-
ther side of the bearing.
c.
Align the 12 tooth sprocket (#2) with the sprock-
et on the feed cup shaft. Lock the sprocket in po-
sition using the sprocket’s set screws.
d.
Install the roller chain (#5) using the Routing
Guide above. Remove excess slack in the chain
with the adjustable idler sprocket (#6).
The right hand drive on 20’ models is installed by re-
peating Steps 2. a. through 2. d.
Rotate each gauge wheel tire several turns while
observing the operation of the entire drive system. If
any chains bind or pop, re-align those sprockets un-
til the drive system turns smoothly.
3.
Recheck all fasteners to see if they are tight, and
that all clips and retainers have snapped into place.
Assembly Illustration
Figure 2-3
13506
Routing Guide
13633