Rack Installation Guide

27

Figure 18.

Installing the Slide Assemblies for Flush-Mount Configuration

9

Secure the front bracket on the slide assembly to the two-post rail with two 12-24 x 0.5-inch
pan-head Phillips screws (see Figure 18).

10

Repeat step 8 and step 9 to install the right slide assembly in the rack.

11

Use an 11/32-inch wrench or nut driver to fully tighten the nuts on the mounting brackets on
both slide assemblies that you tightened with your fingers.

12

Install the stiffening bracket into the appropriate holes at the back of the slide assemblies and
secure the bracket with a 12-24 x 0.5-inch pan-head Phillips screw on each slide assembly
(see Figure 16).
If the vertical rack is 3 inches wide, use the holes at the back end of the slide assemblies
(shown in Figure 16). If the vertical rack is 6 inches wide, use the holes located 3 inches in
front of the holes at the back end of the slide assemblies.

12-24 x 0.5-inch
pan-head
Phillips screw
(4 each slide)

two-post open-frame rack

slide assembly

slide release latch

joined bracket

shoulder screw on
system

system release
latch