Warning – Chamberlain SL 1000-X3 User Manual

Page 31

Advertising
background image

Rev J

Doc 01-20098

Page 31 of 44

D. MAINTENANCE

WARNING

To avoid injury, always turn off the unit power switch before working on gate.

Regular performance of preventive maintenance is essential for reliable system
operation because it corrects small problems before they turn into emergencies.
LiftMaster recommends performing preventive maintenance every 6 to 12 months,
depending upon the amount of gate usage.

If the gate is installed in a private residence or small apartment house where
usage is not severe, yearly preventive maintenance is acceptable.

If the gate is installed in a high-traffic application, semi-annual preventive
maintenance is essential.

1. PREVENTIVE MAINTENANCE TASKS

1.

Gate: must roll freely without any impediment. Check wheels, grease if necessary.

2.

Chain: Check for wear and tension. If loose, adjust chain tension. Do not oil chain.

3.

Sprocket: must not be loose on the shaft. Tighten set screws if loose !.

4.

Idlers: Check for wear. Tighten bolts if loose. Do not oil idler assembly.

5.

Limit switches: contacts must bounce back rapidly when they are pressed and
release. Cam lock plate (see Figure 15) must firmly hold the cams. Do not oil
gearbox shaft.

6.

Belt: Check for wear and tension (25 to 30 lbs.). Adjust the AC motor up or down to
set proper tension.

7.

Pulleys: must all line up and be firmly secured to their shafts. Tighten set screws if
loose !.

8.

Gear Box: Check for no oil leakage around the bushings. Do not oil gearbox.

9.

Control board: Check for water damage or burned spots. All connectors secured to
the board.

10. Wiring: Check all wiring for any insulation damage. Check for loose wire

connections.

11. No Rust: Check for rust throughout the unit. Check corners for water entrapment.

12. Fire Open: Activate Fire department switch to verify emergency gate opening.

13. Gate Sense: Check for the gate sensitivity (refer to Part 2, System Installation,

Section J, Gate Sensitivity Adjustments).

14. Photo-Sensors: Ensure that sensor emitters/receivers are aligned and clean. Verify

that inputs stop gate.

15. Obstruction Alarm: Check for proper operation. Alarm must sound after two

consecutive gate obstruction faults.

NOTES: !: To prevent loosening, LOCTITE threadlocker 242 is applied to set screws.

Advertising