N. FINAL ASSEMBLY OF GATE OPERATOR

Figure 13. Gate Operator Final Assembly

IMPORTANT SAFETY PROCEDURE

1. Turn off power to the gate operator at the circuit breaker and wait for one

minute.

♦ Refer to Figure 13, above, to perform the following instructions.
2. Disconnect Drag Link from Anchor. Then disengage quick disconnect by pulling

the release lever on the Swing Arm Cap Assembly. Remove Swing Arm Cap
Assembly and Drag Link Assembly from drive shaft. Set this assembly aside.

3. Install clear cover on gate operator control box.
4. Make sure that gate operator unit power switch is turned on.
5. Install gate operator cover and secure with four bolts.
6. Replace Swing Arm Cap Assembly and Drag Link Assembly on drive shaft, then

reconnect Drag Link to gate Anchor.

7. Reinstall gate arm assembly onto output shaft/hub. Close red release lever until

engagement pin fully seats into hub and ball plunger engages on handle. This
may require slight side-to-side motion – HANDLE WILL CLOSE WHEN PIN IS
PROPERLY ALIGNED – DO NOT FORCE SHUT.

8. Turn on power to the gate operator at the circuit breaker.
9. Cycle the gate to ensure it is operating properly.