Arbor installation a – New England Arbors VA68111 User Manual
Page 4
4
1915 Dove St., Port Huron MI USA 48060
Toll Free Phone: 1 800 282 9346 Toll Free Fax: 1 877 464 9286
www.edenarbors.com
Move the arbor to its final location (you will need a helper).
When you are satisfied with the location, mark the locations of
the posts, then move the arbor aside and lay it carefully on its side.
Excavate 4 holes approx. 10” deep. Carefully move the arbor back
into position and level it both vertically and horizontally.
Backfill the holes with the excavated soil to cover the anchors.
1
2
A
Into Earth (temporary Installation)
1
B
2
18
6
Similar to the above steps, move the arbor to its final location.
When you are satisfied with the location, mark the locations of
the posts, then move the arbor aside and lay it carefully on its side.
Excavate 4 holes approx. 18” deep, 6“ diameter.
Fill the holes iwth wet cement flush to the ground. You will need 2
bags of pre-mix concrete (purchase separately). Carefully move the
arbor back into position.
Support the arbor and level over the holes with bricks, stones or
bloacks of wood under the bottom rail of the side panel. The post
bottoms should insert themselves approximately 1” into the concrete.
Allow the concrete to set.
1
2
3
B
Into Earth With Concrete Footing
Arbor Installation
A
1
10
6
2
Level
Level