Move the arbor to its final location (you will need a helper).

When you are satisfied with the location, mark the locations of

the posts, then move the arbor aside and lay it carefully on its side.

Excavate 4 holes approx. 10” deep. Carefully move the arbor back

into position and level it both vertically and horizontally.

Backfill the holes with the excavated soil to cover the anchors.

1

2

A

Into Earth (temporary Installation)

1

B

2

18

6

Similar to the above steps, move the arbor to its final location.

When you are satisfied with the location, mark the locations of

the posts, then move the arbor aside and lay it carefully on its side.

Excavate 4 holes approx. 18” deep, 6“ diameter.

Fill the holes iwth wet cement flush to the ground. You will need 2

bags of pre-mix concrete (purchase separately). Carefully move the

arbor back into position.

Support the arbor and level over the holes with bricks, stones or

bloacks of wood under the bottom rail of the side panel. The post

bottoms should insert themselves approximately 1” into the concrete.

Allow the concrete to set.