Cisco CRS Carrier Routing System 8-Slot Line Card Chassis Site Planning Guide

OL-5802-09

Appendix A Preliminary Site Survey

Floor Mounting

How many line card chassis will be
installed? Is there floor space available
for all of the chassis?

Make a sketch of the area where the
chassis is to be installed and note the
chassis location.

Power

Is AC or DC power available for the
chassis? Is there a connection point on the
panel for the chassis?

Is there a fuse access panel (FAP)
available for the equipment? Provide a
connection point on the fuse access panel
for each chassis.

Will a fuse access panel be installed in
time for the routing system installation?
Provide a date when the FAP will be
installed.

Is the FAP in the same room as the
chassis?

Is there an AC power outlet (220 V or

110 V) located within 10 feet of each
chassis for PCs and test equipment?

Is there proper grounding for the
equipment? If not, when will the
grounding be available? Provide a
connection point for the grounding.

Are there any restrictions when the
equipment can be powered on or when
electrical work can be done? If so,
describe them.

Are there special requirements for power
or power cables (for example, a different
wire gauge, and so on)? If so, describe
them.

Table A-1

Sample Preliminary Site Survey (continued)

Preliminary Site Survey