Unit start-up checklist, I. preliminary information, Iii. start-up – Carrier 48TCA04---A12 User Manual
Page 107

107
UNIT START-UP CHECKLIST
I. PRELIMINARY INFORMATION:
MODEL NO.:
DATE:
______________
SERIAL NO: _____________________________________
TECHNICIAN: ___________________________________
BUILDING LOCATION:____________________________
II. PRE-START-UP (insert check mark in box as each item is completed):
j
VERIFY THAT ALL PACKAGING MATERIALS HAVE BEEN REMOVED FROM UNIT
j
VERIFY THAT CONDENSATE CONNECTION IS INSTALLED PER INSTALLATION INSTRUCTIONS
j
VERIFY THAT FLUE HOOD IS INSTALLED
j
CHECK ALL ELECTRICAL CONNECTIONS AND TERMINALS FOR TIGHTNESS
j
CHECK TO ENSURE NO WIRES ARE TOUCHING REFRIGERANT TUBING OR SHARP EDGES
j
CHECK GAS PIPING FOR LEAKS
j
CHECK THAT RETURN--AIR FILTER IS CLEAN AND IN PLACE
j
VERIFY THAT UNIT INSTALLATION IS LEVEL
j
CHECK FAN WHEEL AND PROPELLER FOR LOCATION IN HOUSING/ORIFICE AND VERIFY SETSCREW IS TIGHT
j
VERIFY PULLEY ALIGNMENT AND BELT TENSION ARE CORRECT
III. START-UP
ELECTRICAL
SUPPLY VOLTAGE
L1-L2
L2-L3
L3-L1
COMPRESSOR AMPS
L1
L2
L2
INDOOR FAN AMPS
L1
L2
L2
TEMPERATURES
OUTDOOR-AIR TEMPERATURE
DB
WB
RETURN-AIR TEMPERATURE
DB
WB
COOLING SUPPLY AIR
DB
WB
GAS HEAT SUPPLY AIR
DB
PRESSURES
GAS INLET PRESSURE
IN. WG
GAS MANIFOLD PRESSURE
IN. WG (LOW FIRE)
IN. WG (HI FIRE)
REFRIGERANT SUCTION
PSIG
TEMP _F
REFRIGERANT DISCHARGE
PSIG
TEMP _F
j
VERIFY REFRIGERANT CHARGE USING CHARGING CHARTS
j
VERIFY THAT 3--PHASE SCROLL COMPRESSOR IS ROTATING IN CORRECT DIRECTION
Copyright 2008 Carrier Corp. S 7310 W. Morris St. S Indianapolis, IN 46231
Printed in U.S.A.
Edition Date: 08/08
Manufacturer reserves the right to change, at any time, specifications and designs without notice and without obligations.
Catalog No: 48TC---2SM
Replaces: 48TC--- 1SM
48TC