INSTALLATION

Section 7 - Post Installation

PRIMEPACT 66G and 66LP Recreational Vehicle Cenerators

7.5

INSTALLATION

CHECKLIST

♦ LOCATION AND SUPPORT

l

J Generator is properly located.

U Generator is properly supported.

□ Generator is properly restrained.

♦ GENERATOR COMPARTMENT

□ Coiiipartment construction is proper.

U Holes/Openings are vapror-sealed.

□ Compartment size is correct.

□ Compartment is vapor-sealed.

□ Sound insulation is correct.

□ Floor cutouts are properly completed.

♦ COOLING AND VENTiLATiNG Ali

U Airflow is adequate.

J Air inlet opening is correct.

U Compensate for restrictions.

U Check that installation has been tested.

♦ GASOLINE FUEL SYSTEM

LJ Fuel tank complies with all af)plicable codes.

□ Fuel system is properly installed and checked

for leaks.

♦ OPTIONAL LP GAS

FUEL SYSTEM

□ Fuel system is properly installed and checked

for leaks.

□ Pressure at regulator inlet is correct.

□ Rated flow of primary regulator is correct.

□ All parts are properly installed,

□ Fuel system is properly tested/adjusted.

♦ EXHAUST SYSTEM

□ Exhaust system complies with all applicable codes.

□ Exhaust system is properly and safely installed.

♦ ELECTRICAL CONNECTIONS

□ Connections comply with local code requirements

and all National Electrical Codes.

□ Junction box is properly installed.

□ Wiring meets all standards.

□ All connections are correct.

□ Conduit is properly installed and sealed.

□ Generator is properly bonded to the veliicle.

♦ BATTERY INSTALLATION

□ Recommended battery is installed,

□ Recommended cables are iiistalied.

□ Cables are clean and light.

□ Cables are connected properly.

□ Proper ventilation is proCded.

□ Terminal'’ arp coaled wiib anti-corrosion grease, and

terminal coi' t n< po~,>i'.uied.

♦ OPTIONAL ACCLS

j

ORI

e

S

□ Check that remote start/stop panels (if used) are

installed properly.

□ Check that hour meter kit (if used) is installed

properly.

□ Check that any other options and accessories (if

used) are installed properly.

# POST INSTALLATION TESTS

□ Check that all tests are completed properly.

DATE OF INSTALLATION

NAME OF INSTALLER

SIGNATURE OF INSTALLER

36 Generac* Power Systems, Inc.