9. Attach Flashing: In new construction,

assemble the Chimney Sections to a point

above the roof, then slip the Flashing over

the chimney. On an existing roof, center

and install the Flashing before extending the

chimney above the roof. Allow space to permit

sliding the next Chimney Section up through

the Flashing. Always insure the chimney

remains vertical (use a level), and that at least

a 2” clearance to combustible materials is

maintained all around. Install the upper edge

of the Flashing under the roofing. Nail to the

roof along the upper edge and down each side

with 1” roofing nails. Do not nail the lower

edge of the Flashing (Fig.15). Seal top and

upper sides of flashing with roofing compound

or sealant. Be sure to follow local building

practices, as needed. Seal all nail heads with

a non-hardening waterproof sealant. On flat

or tarred and graveled roofs, nail and seal the

Figure 14

Figure 15

Figure 16

Flat Roof Flashing to the roof on all sides with

roofing compound. Do not put screws through

the Flashing into the Chimney Pipe.

10. Finish Top: Apply a high-temperature

(500ºF), non-hardening waterproof sealant

around the chimney at the point where the

Storm Collar will meet the chimney just

above the Flashing (Fig.15). Slide the Storm

Collar down over the chimney to the top of

the Flashing. Tighten and seal the Storm

Collar against the sealant. After installing

sufficient Chimney Sections to meet the height

requirement (Fig.1), attach the Chimney Cap

onto the top of the chimney by holding the

collar of the cap and twist locking it clockwise

onto the chimney. Do not hold upper portion

of the cap and twist, as this may damage the

cap. The Chimney Cap can be removed for

chimney cleaning as described in the Chimney

Maintenance section of the instructions. Use

an Extended Roof Bracket if the chimney

extends more than 5’ above the roof (Fig.18

in the Extended Roof Bracket section). If

you are located in heavy snow country, it is

recommended that a Snow Splitter be installed

(Fig.16). This will help protect the chimney by

routing snow around it.

SPLITTER

PUSH COLLAR DOWN

TO FLASHING AND

SEAL WITH NON-

HARDENING HIGH

TEMP SILICONE

11. Enclosures: Enclose chimneys where

they pass through occupied spaces, including

closets. Always maintain at least a 2”

clearance between the chimney and any

combustible materials. Interior enclosures