Glow-worm Compact 100E User Manual

Page 13

Advertising
background image

13

221894A

Diagram 6.1

6956

GAS
SERVICE
COCK

HOT
WATER
OUT

COLD
WATER
SUPPLY
IN

HEATING
FLOW

HEATING
RETURN

LEVER (OPEN)
COLD WATER
SUPPLY IN/OUT

SLOT (OPEN)
GAS SERVICE
COCK

LEVER (OPEN)
HEATING
FLOW/ RETURN

SAFETY DISCHARGE PIPE
ROUTING POSITION

The installation requires the following components :-

1.

Plumbing jig Carton

2.

Boiler Carton

3.

Flue Pack

6.1. Plumbing Jig

Remove from the wall template, then follow the instructions
given on the template.

Note: Leaving the service cock bracket (lower jig) fixing screws
loose will make the fitting of the boiler service elbows on to the
service cocks easier. Once the service connections are made,
tighten service cock bracket (lower jig) fixing screws. It is
important that the wall hanging bracket and the service cock
bracket (lower jig) are fitted to a flat and true wall area for correct
alignment with the boiler. If this cannot be achieved it is
acceptable to pack out the service cock bracket (lower jig) to
obtain the correct alignment with the wall hanging bracket.

6.2 Gas Connection

Provision is made for the gas supply to be connected from
below the boiler, see diagrams 1.1 and 6.1 for position.

Refer also to “Gas Supply”, Section 1.7.

Make the gas supply connection to the gas service cock. While
making the connection, do not subject the gas service cock to
heat as you may damage the seals.

6.3 Water Connections

Provision is made for the domestic cold water inlet to be
connected from below or through an internal wall at the rear of
the boiler, see diagram 1.1 and 6.1 for position.

Refer also to Section 5 “Domestic Hot Water System”.

Provision is made for the water connections to be connected
from below or from above, passing down either side of the
boiler. Take care that any pipework connected from above will
clear the expansion vessel. Refer to the wall template. If
connecting from above a vertical piping kit 457160 is available
and is recommended.

NOTE: Top rear flue outlet is not possible with a vertical piping
kit.

If necessary, temporarily fit the boiler.

Flush out the domestic water and heating system before
connecting the boiler.

Make the connections to the domestic hot water outlet and the
heating system by means of the isolating valves, see diagram
6.1.

While making the connections. Do not subject any of the
isolating valves to heat as you may damage the seals.

Make sure that the drain and operating screw heads on the
isolating valves are accessible.

6 Installation Preparation and Gas / Water Connections

6.4 Safety Valve Discharge

WARNING. It must not discharge above an entrance or window
or any type of public access area.

A short discharge pipe is supplied loose with the boiler, which
when fitted to the safety valve, will end below the boiler the
position is next to the heating return, for position see diagram
6.1.

This must be extended, using not less than 15mm od metal
pipe, to discharge, in a visible position, outside the building,
facing downwards, preferably over a drain. The pipe must have
a continuous fall and be routed to a position so that any
discharge of water, possibly boiling, or steam cannot create any
danger to persons, damage to property or external electrical
components and wiring.

Note. To ease future servicing it is advisable to use a compression
type fitting to extend the discharge pipe.

Advertising