Hypertherm HD3070 w/ Automatic Gas User Manual

Page 21

Advertising
background image

1-18

HD3070 w/Automatic Gas Console

20

SPECIFY THE CURRENT SETPOINT CABLE BETWEEN THE POWER
SUPPLY AND THE CUTTING MACHINE INTERFACE or BETWEEN
POWER SUPPLY AND REMOTE CURRENT CONTROL (RCC)

A cable is needed between the power supply and machine interface (if current is set with the
cutting machine computer) or between the power supply and the remote current control unit
(if current is set with the RCC).

Determine if the cutting machine's computer will be setting current or if there will be a remote
current control unit installed to set current. Based on the distance between the power supply
and the cutting machine interface or the RCC, specify the appropriate length cable.

21

SPECIFY THE TIMER-COUNTER CABLE BETWEEN THE POWER
SUPPLY AND THE CUTTING MACHINE INTERFACE or BETWEEN
POWER SUPPLY AND TIMER-COUNTER

A cable is needed between the power supply and machine interface (if monitoring of starts
and errors will be done with the cutting machine computer) or between the power supply and
the timer-counter unit (if monitoring will be done with the timer-counter).

Determine if the cutting machine's computer or the timer-counter will be used. Based on the
distance between the power supply and the cutting machine interface or the timer-counter,
specify the appropriate length cable.

22

SPECIFY THE REMOTE CURRENT CONTROL (RCC) - Optional

Order the RCC only if current is not being set by the cutting machine's computer (see step
20).

23

SPECIFY THE TIMER-COUNTER - Optional

Order the timer-counter only if monitoring of arc starts and errors is not being tracked by the
cutting machine's computer (see step 21).

1-00

Advertising