5. Operation


The system should not be operated by the Operator or personnel authorized by the
Operator until NORTEC Customer Service or its authorized agents have performed
an acceptance inspection of the initial startup. In addition, the Operator must have
received instruction on the operation of the system from DRAABE. After the initial
startup and instruction on operation, it is the responsibility of the Operator to
ensure that only trained personnel operate the system. This is one of the terms of
the warranty from NORTEC.

5.1 Start-up in daily operations


Depending on whether the system was partially or completely shut down, it should
be restarted in reverse order (see also the replacement instructions for the
individual devices). As a general rule, the following applies:

SynPur:

-

First produce the water supply

-

Then produce the power supply

-

Then turn on the mains switch (set to position „I“).



Synthesizing stage:

-

First reconnect the lines


-

Then produce the water supply



CO

2 gas

:

-

First connect the gas lines


-

Then open the valves and set to 6 bar (87 psi).