IV. Fastening retaining nut of anchor plate

Fasten the retaining nut of the anchor plate on the anchor plate according to part B in
Figure B-33, and then fasten the bolt force moment to 45 Nm.

B.3.9 Insulation Test

Measure the resistance value between the retaining bolt and the anchor plate with a
Multimeter. If the resistance value measured is larger than five meg-ohm, it means that
the insulation is normal. Otherwise, it means that the cabinet is not insulated from the
earth. In this case, remove all anchor plate parts to check whether the insulating
covering or insulating washer is installed or whether the insulating parts are damaged.
Afterwards, reinstall the anchor plate and repeat the insulation test.

B.3.10 Floor Recovery

According to the actual site status, cut the raised floor around the cabinet and then
recover the floor. Figure B-34 shows the raised floor recovery installation and Figure
B-35
shows the B68-22 cabinet installation in the equipment room with the raised floor.

Caution:

The framework of the raised floor can be installed on the side floor bracket according to
the actual circumstance, as shown in Figure B-34.
Cut the raised floor as little as possible.