The country data set must be set correctly.
If you select a country data set which is not valid for your country and purpose, it can cause a
disturbance in the PV system and lead to problems with the grid operator. When selecting the
country data set, you must always observe the locally applicable standards and directives as
well as the properties of the PV system (e.g. PV system size, grid-connection point).

• If you are not sure which country data set is valid for your country or purpose, contact

your grid operator for information on which country data set is to be configured.

The basic procedure for changing operating parameters is explained in another section (see
Section 8.2 "Changing Operating Parameters", page 40)
.

Procedure:

• Select the parameter Default or Set country standard and adjust the required country data

set.

8.5

Deactivating Grounding Conductor Monitoring

If the inverter is to be installed in an IT network or another grid configuration in which deactivation
of the grounding conductor monitoring is required, deactivate the grounding conductor monitoring
as follows.
The basic procedure for changing operating parameters is explained in another section (see
Section 8.2 "Changing Operating Parameters", page 40)
.

Procedure:

• Set the parameter PE connection monitoring or PEOpnMon to Off.

8 Configuration