43. Pull out E-Stop on side of control console, Inverters should initialize, alert

window appear on desktop of CPU and then go away, you should have heard the
brake solenoids cycle on the pitch and roll motors.

NOTE: When raising unit for the first time, have
people watch both slip ring sides to insure that
during raising phase none of the cables bind
anywhere. Should cable bind, immediately STOP
the raising and clear the problem.


44. Turn to Technical Manual page 7 paragraph 2-3 and perform a motor initial phase

test to verify all motor connections and that motor rotation is correct. When all
tests are completed successfully, lower unit to the support stands.

45. Initiate the program using the normal startup procedures in Operations Manual,

page 4 paragraph 2-2. Run several test cycles to verify performance of the unit.

46. Perform the final leveling and squaring of the unit. When squared and level

anchor the base C channels using the anchors or glue pads provided. See DET-
008

47. Perform another cycle test after unit anchoring procedure is completed.

48. Correctly route and detail all cabling, install walkway covers over floor cabling.

Install and verify all protective panels on the lift system and side of A frame
cabinetry. DET-009

49. Partially raise the unit .Install the tail boom cover and secure with two plastic

covered wings nuts and washers lower rear of cover. Insure wing nuts are tight.
Lower unit back down. DET-010

50. Install the Tail enclosure panel over center weldment. DET-011

51. Complete the field installation checklist, operator training checklist and

maintenance training checklist.

52. Verify ID plates are posted inside lower door of the control console.