GB300 BOILER INSTALLATION AND OPERATION INSTRUCTIONS

Page 22

Figure 43

“J” Bolt Installation

CAST IRON PRESSURE TEST

NOTE: Before filling the sections with water
temporarily set the flue collector(s) on top of the
sections to locate the flue collector brackets, Figure
44. On 13 to 21 section models attach the top jacket
splice panel bracket, Figure 45. Also mark the
intermediate casting that the flue collectors rest on.

Install a valve in the top and bottom tapping of the left
end section to vent any trapped air and allow boiler
draining after pressure test completion. Connect a water
pressure gage sized for the required test pressure to one
of the end castings. Plug all the other tapped openings.
Fill the cast iron sections with water leaving the top valve
open until all of the air has been bled from the sections.

Figure 44

Flue Collector Bracket Installation

Figure 45

Top Jacket Splice Panel Bracket