GB300 BOILER INSTALLATION AND OPERATION INSTRUCTIONS

Page 29

The jacket should be assembled using the black screws
provided. On 5 through 12 section models slide the rear
panel behind the draft hood flanges with the grill side on
the floor, Figures 68, 69 & 70. On 13 to 21 section boilers
open Box 55185, Jacket Splice Box, Figure 71. Screw
the two rear jacket panels to the rear jacket panel splice
panel, Figure 72, before sliding the panels behind the
draft hoods.

Figures 68

Rear Panel Installation, 5 through 12

Figures 69

Rear Panel Installation, 5 through 12

Figures 70

Rear Jacket Panel Installation Detail

Figures 71

Box 72694, Jacket Splice Box

Figures 72

Rear Panel Installation, 13 through 21

Fasten the rear jacket panel(s) to the inner draft hood
and flue collector flanges using the holes provided,
Figure 73.

Figures 73

Rear Panel Installation