Chapter 2: Server Installation

2-3

2-4

Installing the SuperServer 6012L-6 into a Rack

This section provides information on installing the SuperServer 6012L-6 into

a rack unit. If the 6012L-6 has already been mounted into a rack, you can

skip ahead to Sections 2-5 and 2-6. There are a variety of rack units on

the market, which may mean the assembly procedure will differ slightly.

The following is a guideline for installing the 6012L-6 into a rack with the

rack rails provided. You should also refer to the installation instructions

that came with the rack unit you are using.

Identifying the Sections of the Rack Rails:

You should have received two rack rail assemblies with the SuperServer

6012L-6. Each of these assemblies consist of three sections: an inner

fixed chassis rail that secures to the 6012L-6 (A) and an outer fixed rack

rail that secures directly to the rack itself (B). A sliding rail guide sand-

wiched between the two should remain attached to the fixed rack rail.

(See Figure 2-1.) The A and B rails must be detached from each other to

install.

To remove the fixed chassis rail (A), pull it out as far as possible - you

should hear a "click" sound as a locking tab emerges from inside the rail

assembly and locks the inner rail. Then depress the locking tab to pull

the inner rail completely out. Do this for both the left and right side rack

rail assemblies.

Figure 2-1. Identifying the Sections of the Rack Rails