Wiring Connections 21

9.0

W

IRING

C

ONNECTIONS

Refer to the drawings in this manual and any other drawings provided by Liebert for this installa-

tion. Make all of the following connections:
1. AC power cables from input power source circuit breaker (RIB) to UPS Module Input. Observe

phase rotation.

2. AC power cables from bypass power source circuit breaker (BIB) to UPS Module Bypass

input. Observe phase rotation.

3. AC power cables from UPS Module Output to critical load. Observe phase rotation.

!

WARNING
VERIFY THAT ALL INCOMING HIGH AND LOW VOLTAGE

POWER CIRCUITS ARE DE-ENERGIZED AND LOCKED OUT

BEFORE INSTALLING CABLES OR MAKING ELECTRICAL

CONNECTIONS.
ALL POWER CONNECTIONS MUST BE COMPLETED BY A

LICENSED ELECTRICIAN EXPERIENCED IN WIRING UPS

EQUIPMENT, AND IN ACCORDANCE WITH ALL APPLICABLE

NATIONAL AND LOCAL ELECTRICAL CODES.
IMPROPER WIRING MAY CAUSE DAMAGE TO THE UPS OR

INJURY TO PERSONNEL.

!

CAUTION
All shielded cables, non-shielded cables, non-shielded control

wires, non-shielded battery breaker control wires, and non-

shielded remote control wires must be housed in individual,

separate, steel conduits. Placing multiple cables in the same

conduit with other control or power wiring may cause system

failure.

!

CAUTION
If there are line-to-neutral loads connected to the UPS output, the

input source must be wye connected and have three phases plus

neutral plus ground. If the specified input is not available, an

isolation transformer is required.

NOTE
If your installation includes a Maintenance Bypass Panelboard or a

Transformer Cabinet, some (or all) power cables will be terminated in these

cabinet(s). Make sure all required wiring between UPS module and the

optional cabinet(s) is completed. Observe phase rotation.