Installation – Lopi Direct Vent Freestanding Stove User Manual

Page 19

Advertising
background image

Installation

(for qualified installers only)

1 9

Travis Industries

1 0 0 - 0 1 1 8 7 _ 0 0 0

4 0 7 0 2 1 9

Vent Termination Requirements (see illustration below)

!

Venting terminals shall not be recessed into a wall or siding.

A

Minimum 9" clearance from any door or window

B

Minimum 12" above any grade, veranda, porch, deck or balcony

C

Minimum 3-3/8" from outside corner walls
NOTE: Clearance in accordance with local installation codes and the requirements
of the gas supplier.

D

Minimum 12" from inside corner walls
NOTE: Clearance in accordance with local installation codes and the requirements
of the gas supplier.

11” Min.

6” Min.

Roof
Surface

Roof
Eaves

E

Minimum 11" clearance below unventilated soffits or roof surfaces
Minimum 18" clearance below ventilated soffits
Minimum 6" clearance below roof eaves
NOTE: Vinyl surfaces require 24"
NOTE: Clearance in accordance with local installation codes and the requirements of the gas supplier.

F

Minimum 12" clearance below a veranda, porch, deck or balcony
NOTE: Permitted only if veranda, porch, deck, or balcony is fully open on a minumum of two sides beneath the floor.
NOTE: Clearance in accordance with local installation codes and the requirements of the gas supplier.

G

Minimum 48" clearance from any adjacent building

H

Minimum 84" clearance above any grade when adjacent to public walkways or driveways
NOTE: may not be used over a walkway or driveway shared by an adjacent building

I

Minimum 48" clearance from any mechanical air supply inlet

J

Minimum 36" clearance above and 48” below and to the sides of non-mechanical air supply inlet

K

Minimum 36" from the area above the meter/regulator (vent outlet)
NOTE: Clearance in accordance with local installation codes and the requirements of the gas supplier.

L

Minimum 36" from the meter/regulator (vent outlet)
NOTE: Clearance in accordance with local installation codes and the requirements of the gas supplier.

M

Minimum 12” above the roof line (for vertical terminations)

N

Minimum 24” horizontal clearance to any surface (such as an exterior wall) – for vertical terminations

C

B

H

E

G

A

D

F

L

K

J

I

NOTE: Measure clearances to the nearest edge of the exhaust hood.

A

E

E

M

N

Use the vinyl siding standoff (#1250) when installing on an exterior with vinyl siding.

Vent termination must not be located where it will become plugged by snow or other material

Advertising