Order of Installation

The order of software package installation is important. The typical NMS installation is an upgrade
from a pre-existing 6800 Series NMS. To properly install the NMS on the host processor for a site
already running a previous release of the NMS, follow the order of general steps defined below:

1. Backup the existing database.

2. Load the seven volume set of 6800 NMS Application software (Release 4.2).

3. Load the PTF base software (Release 4.2.1).

4. Optionally, load any required peripheral software packages for the Altos 5000 platform.

ANALYSIS Gateway Option

3270 Terminal Emulation

Token Ring Option

5. Run the migration procedure using the backed up existing database.

6. Backup the new migrated database.

7. Load the ACCULINK Network Manager Application software (Release 4.3.0).

8. Restore the migrated database.

First-time installation order is simpler. To properly install th NMS on the host processor for the
first time, follow the order of general steps defined below:

1. Load the seven volume set of 6800 NMS Application software (Release 4.2).

2. Load the PTF base software (Release 4.2.1).

3. Optionally, load any required peripheral software packages for the Altos 5000 platform.

ANALYSIS Gateway Option

3270 Terminal Emulation

Token Ring Option

4. Load the ACCULINK Network Manager Application software (Release 4.3.0).