Venting installation tips, Venting configurations – Raypak 500 User Manual

Page 25

Advertising
background image

25

U.S. Installations

Refer to the latest edition of the National Fuel Gas

Code.

Vent termination requirements are as follows:

1. Vent must terminate at least 4 ft below, 4 ft hori-

zontally from or 1 ft above any door, window or

gravity air inlet to the building.

2. The vent must not be less than 7 ft above grade

when located adjacent to public walkways.

3. Terminate vent at least 3 ft above any forced air

inlet located within 10 ft.

4. Vent must terminate at least 4 ft horizontally, and

in no case above or below unless 4 ft horizontal

distance is maintained, from electric meters, gas

meters, regulators, and relief equipment.

5. Terminate vent at least 6 ft away from adjacent

walls.

6. DO NOT terminate vent closer than 5 ft below roof

overhang.

7. The vent terminal requires a 12 in. vent terminal

clearance from the wall.

8. Terminate vent at least 1 ft above grade, including

normal snow line.

9. Multiple direct vent installations require a 4 ft

clearance between the ends of vent caps located

on the same horizontal plane.

Installations in Canada

Refer to latest edition of the B149 Installation Code.

A vent shall not terminate:

1. Directly above a paved sidewalk or driveway

which is located between two single-family dwell-

ings and serves both dwellings.

2. Less than 7 ft (2.13 m) above a paved sidewalk or

paved driveway located on public property.

3. Within 6 ft (1.8 m) of a mechanical air supply inlet

to any building.

4. Above a meter/regulator assembly within 3 ft (915

mm) horizontally of the vertical centerline of the

regulator.

5. Within 6 ft (1.8 m) of any gas service regulator

vent outlet.

6. Less than 1 ft (305 mm) above grade level.

7. Within 3 ft (915 mm) of a window or door which

can be opened in any building, any non-mechani-

cal air supply inlet to any building or the

combustion air inlet of any other appliance.

8. Underneath a verandah, porch or deck, unless the

verandah, porch or deck is fully open on a mini-

mum of two sides beneath the floor, and the

distance between the top of the vent termination

and the underside of the verandah, porch or deck

is greater than 1 ft (305 mm).

Venting Installation Tips

Support piping:

horizontal runs—at least every 5 ft (1.5m)

vertical runs—use braces

under or near elbows

Venting Configurations

For heaters connected to gas vents or chimneys, vent

installations shall be in accordance with the NFGC

(U.S.), or B149 (Canada), or applicable provisions of

local building codes.

Vertical Venting (Category IV)

WARNING: Examine the venting system at least

once a year. Check all joints and vent pipe

connections for tightness, corrosion or deterioration.

CAUTION: This venting system requires the

installation of a condensate drain in the vent piping

per the vent manufacturer’s instructions. Failure to

install a condensate drain in the venting system will

void all warranties on this boiler.

WARNING: The Commonwealth of Massachusetts

requires that sidewall vented heaters, installed in

every dwelling, building or structure used in whole or

in part for residential purposes, be installed using

special provisions as outlined on page 53 of this

manual.

Advertising
This manual is related to the following products:

300, 850