Installation

Figure 11

- Typical Piping Arrangement For Direct Space Heating and Domestic Water Supply with Tankless

Water Heater. Open Loop

Piping Configuration

When employing a Tankless Water Heater in a
combination hydronic hot water heating system, the
system is considered an Open Loop System; i.e. the
system must be configured to simultaneously deliver
both domestic hot water and space heating. By
definition, if the circuit is sealed off from the
atmosphere at all locations (as is true for most modern
hydronic systems) it is called a closed loop system.
Conversely If the circuit is open to the atmosphere at
any point

, it is called an open loop system. Current

Rinnai tankless products are not certified for closed
loop applications. Furnaces may be used in closed
loop application only with the new Rinnai Condensing
Boilers. Refer to Boiler Manuals for more details.

Open Loop System

If piping is done in accordance with the recommended
schematic diagram shown in Figure 11, the following
purge and priming procedure applies.

PURGING AND PRIMING THE SYSTEM:

The following procedure describes how the Rinnai®
system may be piped to eliminate the need for a
“purge cart” to fill the system and remove entrapped

air bubbles.

STEP 1:

CLOSE the air separator venting valve.

STEP 2:

CLOSE ball valve 3 (BV

3

);

STEP 3:

OPEN drain valve 3 (DV

3

) to which a hose

MUST be connected and draining to a sink, drain or
outdoors.

STEP 4:

CLOSE drain valves 1 & 2 (DV

1

and DV

2

)

and OPEN ball valve 2 (BV

2

).

STEP 5:

OPEN cold water supply main valve (ball

valve 1 - BV

1

). The system will begin the prime/purge

process using the street pressure. Entrapped air
bubbles being pushed out of the system will be evident
by a slight vibration of the discharge hose connected
to drain valve 3 (DV

3

). The hose will stop vibrating

when laminar flow is achieved.

STEP 6:

CLOSE drain valve 3 (DV

3

);

STEP 7:

OPEN ball valve 3 (BV

3

). The system is now

purged, primed and ready to go.

STEP 8:

OPEN the air separator venting valve.

Note:

For an open loop system, use expansion tank

approved for potable water use only.

All piping to be 3/4 inch.