ii. Remove existing nozzle from nozzle adapter.

iii. Insert the proper NOZZLE into NOZZLE

ADAPTER and tighten securely (Do not

cover tighten).

iv. Replace adapter, with nozzle installed, into

drawer assembly and secure with screw (1).

c. Inspect and measure burner electrodes. Refer

to Figure 6 for the proper electrode settings.

Figure 6: Electrode Setting

d. Re-install Drawer Assembly into Combustion

Head per Step 4a above.

e. Insertion Depth, verify the distance between

the tip of the end cone is equal to the distance

specified in Table 9A.

f. Turbulator Setting, refer to Figure 7.

Figure 7: Turbulator Setting

g.

Pump Connections and Port Identification,

refer to Figure 8.

Figure 8: Pump Connections and Port Identification

This burner is shipped with the oil pump set

to operate on a single line system. To operate

on a two-line system the bypass plug must be

installed.

WARNING: Do not operate a single line

system with the by-pass plug installed.

Operating a single line system with the by-pass

plug installed will result in damage to the pump

shaft seal.

NOTE: Pump pressure was factory pre-set but

must be checked at time of burner start-up. A

pressure gauge is attached to the PRESSURE/

BLEEDER PORT (7) for pressure readings.

Two PIPE CONNECTORS (4) are supplied

with the burner for connection to either a single

or two-line system. Also supplied are two

ADAPTORS (3), two female ¼” NPT to adapt

oil lines to burner pipe connectors. All pump

port threads are British Parallel Thread design.

Direct connection of NPT threads to the pump

will damage the pump body.

Riello manometers and vacuum gauges

do not

require any adapters, and can be safely connected

to the pump ports. An NPT x metric adapter

must be used when connecting other gauge

models.

h. Replace Burner Cover and Tighten Burner

Cover Screws.

F.

INSTALL WATER BOILER TRIM AND CONTROLS,

(see Figures 1A and 1B)
1. Install return piping supplied with boiler. Apply

Teflon or Sealant to all joints prior to assembly.

Thread 1½" NPT x 5" Lg. return nipple into 1½"

NPT tapping located in lower left corner of front

section. Thread 1½" x ¾" x 1½" NPT tee onto

5" nipple. Thread ¾" drain valve into ¾" NPT

connection on tee. Tighten all joints with wrench

until water tight and 1½" NPT return connection on

tee is facing away from boiler horizontally to allow

for proper burner swing door clearance, see Figures

1A, 1B and Figure 9.