5 Connecting to power supply and bus system

VEGAPULS SR 68 • Modbus and Levelmaster protocol

41371-EN-130624

Terminal

Function

Polarity

1

Voltage supply

+

2

Voltage supply

-

3

Modbus-Signal D0

+

4

Modbus-Signal D1

-

5

Function ground with installa-

tion according to CSA

5.4 Switch-on phase

After VEGAPULS SR 68 is connected to the bus system, the instru-

ment carries out a self-test for approx. 30 seconds. The following

steps are carried out:

Internal check of the electronics

Indication of the instrument type, hardware and software version,

measurement loop name on the display or PC

Indication of the status message "F 105 Determine measured

value" on the display or PC

Status byte goes briefly to fault value

As soon as a plausible measured value is found, it is outputted to the

signal cable. The value corresponds to the actual level as well as the

settings already carried out, e.g. factory settings.