4. Installation







4.1 Moving to The Installation Site

The series UPS has wheels making it easy to move the UPS to the

installation site after it has been unpacked. However, if the receiving

area is far from the installation site, it is recommended to move the

UPS by using a pallet jack or a truck before unpacking the UPS.

4.2 Unpacking and Inspection

1. At the installation site, the utmost care shall be taken when

removing the packaging in order to avoid damaging the equipment.

Cut the plastic poly-straps around the shipping container and

remove the corrugated carton and the PS foam on the top of the

UPS. With one or two people on each side of the UPS, lift the UPS

out of the pallet.

Warning: the plastic poly-straps around the shipping container

are under tension. While cutting, don’t face to them, they will

spring back and may cause eye injury.

The shipping materials are recyclable. After unpacking,
save them for later use or dispose of them appropriately.

The system may be installed and wired only by qualified
electricians in accordance with applicable safety regulations!

When installing the electrical wiring, please note the nominal
amperage of your incoming feeder.