EntelliGuard R Circuit Breaker Retrofill AKD-8 Installation Manual DEH-41549 02/12

Modify Retrofill

WIRING

Before installing the breaker, the

secondary disconnects must be wired to

the EntelliGuard Breaker.

Wires with wire markers are provided on

the retrofil. Make sure that the switchgear

wiring connection points match up with

the original wiring of the cubicle. This

ensures that all wiring connections are

properly made.

Wrong connections will cause the breaker

to malfunction.

Modify AKD-8—AKR30S Switchgear Compartment, Only

It must be ensured that the supply power

to the compartment is turned off/

compartment is de-energized for all the

incoming and outgoing circuits of the LVS

prior to any work being conducted on it.

During the installation and related work on

the equipment, it must be ensured that the

operator is using the prescribed PPE for the

specified tasks.

Ensure only qualified personnel install, operate, service, and maintain all electrical

equipment.