GE Industrial Solutions EntelliGuard R AKD-8 User Manual

Page 41

Advertising
background image

40

EntelliGuard R Circuit Breaker Retrofill AKD-8 Installation Manual DEH-41549 02/12

Figure 34. Neutral Bus Rogowski ASM 10108266

Procedures

PRODUCT DAMAGE

Write down the orientation of the existing Iron

core CT and the polarity of the connections.
The orientation and polarity needs to be

matched when the air core Rogowski is
assembled in the cable compartment.Do not
allow the circuit breaker to hit a hard surface

while handling.

1. Ensure that the LVS has been de-energized and the breaker in the compartment being retrofit are

switched off and removed from the LVS.

2. Open the door on the rear of the compartment to access the Cable/ Bus compartment of the LVS
3. Note that he existing neutral CT assemblies are usually mounted vertically on two copper bus bars

placed horizontally.

4. Disconnect the wires that are attached to the existing CT assemblies and place them such that they do

not interfere with the replacement of the CT assemblies.

5. Unfasten and remove the bolts that hold the neutral disconnect assemblies to the horizontal bus bars.

Keep the hardware in a secure location for reassembly.

6. Be careful while handeling the CT assemblies such that they do not fall down or damage other

components within the LVS.