7 OPERATION

START UP AND COMMISSIONING


A GE GLOBAL SERVICES FIELD ENGINEER must perform start-up and

commissioning of the UPS. Please Contact GE. Global Services at least
two weeks prior to schedule start-up and commissioning at 1-800-637-
1738, or by E-mail at

[email protected]

.



This symbol refers to the operations of a parallel system.



NOTE !

Verify for correct input/output cabling before connecting Utility to the
UPS.
Open only the front door, do not remove any panels.

Check after every step for correct reaction of the UPS (LED’s on the
panel), and correct voltage and current measurements, before you
proceed to the next step.



NOTE !

All operations (including start-up, shutdown, removing/adding a unit
from/to a Parallel System) MUST BE PERFORMED with eBoost™ Operation
Mode
DISABLED.



Find on the following pages the descriptions of the various procedures of start-up and
shutdown for UPS single
and UPS Parallel System, divided into the following principal
chapters:

7.1

PROCEDURES FOR SINGLE SG Series 750 & SG Series 750 T12


7.2 PROCEDURES

FOR

SG Series 750 & SG Series 750 T12 PARALLEL SYSTEM