Operating Manual SG Series 100 – 120 - 150 kVA

7.4.7 Restore to normal operation after “total off”

View of the panel after pressing the button total off.

All Contacts are open.

Rectifier, Inverter and Static-Switch shutdown.

First operated unit

All other units of the system



1. Reset total off by pressing and holding the “total offbutton and then the inverter

on ( I ) key, on any of the Units simultaneously, until Load is supplied from Bypass and
the Rectifiers start.

• System output connects to Bypass Utility.

Rectifiers start with blinking LED.

• At the end of Soft-start the LED’s remains lit.

• The LCD screen

on all Units

shows: “LOAD ON BYPASS”.

First operated unit

All other units of the system

2. Connect the Battery to all Units by closing the external Battery Switch(es) or Fuses.