GE Industrial Solutions SG Series 50 & 80 kVA Operating Manual User Manual

Page 63

Advertising
background image

Modifications reserved

Page 63/82

OPM_SGS_USM_50K_80K_0US_V030.doc

Operating Manual SG Series 50 & 80 kVA

7.3.8 Restore to normal operation after EPO (Emergency Power Off)

UPS panel after activation of EPO
(Emergency Power Off)
with Utility not
available, i.e. complete shutdown of the

UPS and LCD screen OFF.
In this case wait until Utility
is again
available, then proceed to restart the UPS
as described below Points 1 through 3.


UPS panel after activation of EPO (Emergency Power Off) with Utility available.
All Contacts are open. Rectifier, Inverter and Static-Switch shutdown.

First operated unit

All other units of the system

1. Reset the EPO (Emergency Power Off) button.

Press mute, to reset alarm and buzzer.

First operated unit

All other units of the system

2. Press inverter off ( O ) key on all Units.

Rectifiers start with blinking LED.
• After pressing the “inverter off” key on the last unit of the parallel system, the output of

all Units connect to Bypass Utility.

The LCD screen shows: “LOAD ON BYPASS”.

First operated unit

All other units of the system

Continue

Advertising