To find Follower Setpoint 1 (CP-03) for Example B:

Follower E.U. desired

Setpoint 1

=

________________________________

x

100 (%)

Lead E.U. operation

10 gal/min

The Follower Engineering Units (gallons/minute of ingredient B)
at which you want the Follower to operate - do not confuse this
with the full capacity that the Follower is capable of pumping.

Divided by

20 gal/min

The Lead Engineering Units (gallons/minute of ingredient A)
that the Lead is operating at - do not confuse this with the full
capacity that the Lead is capable of operating at.

Multiplied by 100 (%) Equals

50

Follower Setpoint 1 (CP-03) value.

To find Follower Setpoint 2 (CP-04) for Example B:

Follower E.U. desired

Setpoint 2

=

________________________________

x

100 (%)

Lead E.U. operation

7 gal/min

The Follower Engineering Units (gallons/minute of ingredient B)
at which you want the Follower to operate - do not confuse this
with the full capacity that the Follower is capable of pumping.

Divided by

10 gal/min

The Lead Engineering Units (gallons/minute of ingredient A)
that the Lead is operating at - do not confuse this with the full
capacity that the Lead is capable of operating at.

Multiplied by 100(%) Equals

70

Follower Setpoint 2 (CP-04) value.