FRAME BRACKET ASSEMBLY (1200 and 1500 lb kits only, shown in Fig. 5)
•Assemble 5/8” bolt (V) through the top holes of the outside frame bracket (T) and inside frame
bracket (U) shown in Fig. 5.
•Slide bracket assembly over the trailer frame and install two 5/8” bolts through the highest lower
bolt holes that are unobstructed by the frame. Install three 5/8” nuts (AB) and hand tighten.
•Slide frame brackets into position, the center of the frame brackets should be placed as shown in
Fig. 6. See Chart 1 on page 3 for dimension specification.
•Insert shoulder bolt (Y) through the pad hanger (M) and outside frame bracket. Frame brackets
have four mounting holes used for 4, 5, and 6” tall frames. Insert the shoulder bolt through the
highest hole not obstructed by the frame.

NOTE: During spring bar setup, it may be necessary to use a lower bracket hole to decrease
spring bar load if there is not enough head angle adjustment.

•Assemble 5/8” nut to the shoulder bolt clamping the pad hanger to the outside frame bracket.
•Torque all 5/8” nuts to 120 ft*lbs.
•Repeat for the other side.