Trouble Shooting

When properly installed in accordance with the
original design specifications Warner Electric
tensioncells should require little or no regular
maintenance or service.

Certain conditions, however, can impair their
inherently accurate and reliable performance.
Therefore, if trouble should arise, the following
conditions should be checked.

1. Has the tension measuring system been

changed?

a. An increase or decrease in strip tension.

b. An increase or decrease in the wrap

angle.

If the above parameters have been
changed enough to prevent the unit from
operating within the limits of the fixed
Mechanical Stop, restore parameters to
previous condition or consult factory.

2. Is the loadcell mounted securely?

3. Is tension measuring roll in proper alignment

and does it turn freely?

4. Are bearings and seals free of all binding

and stickiness? Are they worn?

3. Are LVDTs open or shorted?

To check, turn off power and disconnect the
input and output leads. Check coil continuity
and resistance. (Refer to Figure 10)

a

Pin A to Pin B (Primary Coil) should be in
excess of 2 megohms.

b. Pin A or Pin B to LVDT shell should be in

excess of 5 megohms.

c. Pin C to Pin D (Secondary Coil) should

be approximately 20,000 ohms.

d. Pin C or Pin D to LVDT shell should be in

excess of 5 megohms.

If LVDT circuits are open or shorted, replace
LVDT. Contact Warner Electric with tensioncell
model number and serial number.

Black - (2)

Red + (1)

Green (3)

Blue (4)

Input

Output

X Twisted Leads

A B

Oscillator

Demodulator

P1

S1

S2

X

X

When Supplied

with Cable

(1) Red + DC
(2) Black – DC

(3) Green – Signal
(4) White + Signal

C D

B
A

C
D

Electrical

1. Are LVDTs receiving correct input voltage?

Check line voltage, fuses or circuit breakers,
and power switches. Check power supply
output and voltage to LVDTs.

2. Are all connections secure?

Check for continuity. Retighten all connec-
tions. Recheck operation.

Figure 10