5 conduit/cable installation, 6 detector/source mounting, 1 tilt kit p/n 888270 – Spectrex Quasar 900 Open-Path Gas Detection System User Manual

Page 41: 2 detector/source installation, Conduit/cable installation, Detector/source mounting, Tilt kit p/n 888270, Detector/source installation, Table 10: tilt mount kit

Advertising
background image

TM 888200 Rev (I), January 2014

Conduit/Cable Installation

29

5.5

Conduit/Cable Installation

The conduit and cable installation must comply with the following guidelines:

1

To avoid water condensation in the detector, it should be installed with
the conduits/cable entries facing downwards.

2

Use flexible conduits/cables for the last portion connecting to the
detector.

3

When pulling the cables through the conduits, ensure that they are not
tangled or stressed. Extend the cables about 12 inches (30cm) beyond
the Detector location to accommodate wiring after installation.

4

After the conductor cables have been pulled through the conduits,
perform a continuity test.

5.6

Detector/Source Mounting

The Detector Source should be mounted with the Tilt Mount Kit, Model
888270. The Tilt enables the Detector to be rotated up to 45º in all
directions and fine alignment of up to 3º.

5.6.1 Tilt Kit P/N 888270

The following contents are included with the Tilt Mount Kit:

Table 10: Tilt Mount Kit

Item

Qty

Type/Model

Tilt Mount

1

888269

Screw

1

M10 x 1.5

Spring Washer

1

No. 10

5.6.2 Detector/Source Installation

(Figure 4 and Figure 5)

The detector and the source can be installed in two ways with the same Tilt
Mount.

To install the Detector/Source:

1

Place the Tilt Mount holding plate (item 1) in its designated location and
secure it with (4) fasteners through four (4) holes dia. 8.5mm.

Notes:

Skip this step if the Tilt Mount is already installed.

Detector removal for maintenance purpose does not require
Tilt Mount removal.

Advertising