Installation

Auxiliary-piping checklist

Precautions

WARNING:

• Cooling systems such as those for bearing lubrication and mechanical-seal systems must be

operating properly to prevent excess heat generation, sparks, and premature failure.

• Sealing systems that are not self-purging or self-venting, such as plan 23, require manual venting

prior to operation. Failure to do so will result in excess heat generation and seal failure.

NOTICE:
The mechanical seal must have an appropriate seal-flush system. Otherwise, excess heat
generation and seal failure can occur.

When to install

You may need to install auxiliary piping for bearing cooling, seal-chamber cover cooling,
mechanical seal flush, or other special features supplied with the pump. Consult the pump data
sheet for specific auxiliary piping recommendations.

Checklist

Check

Explanation/comment

Checked

Check that the minimum flow for

each component is 1 gpm (4 lpm).
If the bearing and seal chamber
cover cooling are provided, then
the auxiliary piping must flow at 2
gpm (8 lpm).
Check that the cooling water pres- –
sure does not exceed 100 psig
(7.0 kg/cm

2

).

Final piping checklist

Check

Explanation/comment

Checked

Check that the shaft rotates

Rotate the shaft by hand. Make

smoothly.

sure there is no rubbing that can
lead to excess heat generation or
sparks.

Re-check the alignment to make

If pipe strain exists, then correct

sure that pipe strain has not

the piping.

caused any misalignment.

XHD Installation, Operation, and Maintenance Manual

39