Joint Cementing Procedure

All cementing of joints should be done according to the

specifications outlined in ASTM D 2855.

1. Measure and cut vent pipe to desired length.

2. Debur and chamfer end of pipe, removing any ridges or

rough edges. If end is not chamfered, edge of pipe

may remove cement from fitting socket and result in a

leaking joint.

3. Clean and dry surfaces to be joined.

4. Test fit joint and mark depth of fitting on outside of pipe.

5. Uniformly apply a liberal coat of PVCD primer for PVC

or use a clean dry cloth for ABS to clean inside socket

surface of fitting and male end of pipe to depth of fitting

socket.

NOTE: Time is critical at this stage. Do not allow primer to

dry before applying cement.

DANGER OF EXPLOSION!

Fumes from PVC glue may ignite during system check.

Allow fumes to dissipate for at least 5 minutes before

placing unit into operation.