NOTE: If necessary the condensate trap may be installed

up to 5’ away from the furnace. Use PVC pipe to connect

trap to furnace condensate outlet. Piping from furnace must

slope down a minimum of 1/4” per ft. toward trap.

1. Determine which side condensate piping will exit the

unit, location of trap, field-provided fittings and length of

PVC pipe required to reach available drain.

2. Remove plug (Figure 41) from the cold end header box

at the appropriate location on the side of the unit. Install

field-provided 1/2 NPT male fitting into cold end header

box. Use Teflon tape or appropriate pipe dope.

3. Install the cap over the clean out opening at the base of

the trap. Secure with clamp. See Figure 44.

4. Install drain trap using appropriate PVC fittings, glue all

joints. Glue the provided drain trap as shown in Figure

44. Route the condensate line to an open drain.

Condensate line must maintain a 1/4” downward slope

from the furnace to the drain.

5. Installed field provided vent on trap assembly as shown

in Figures 42 through 45. Trap must extend at least 1”

above the furnace condensate drain connection in upflow

applications and 4-1/2” above the bottom of the cabinet

in horizontal applications.

6. If unit will be started immediately upon completion of

installation, prime trap per procedure outlined in Unit

Start-Up section.

CONDENSATE TRAP AND PLUG LOCATIONS

(Unit shown in upflow position)

NOTE: In upflow applications where side return air filter is installed

on same side as the condensate trap, filter rack MUST be installed

beyond condensate trap or trap must be relocated to avoid

interference.