Danger, Warning – Howard HI-102 Overhead Transformer User Manual

Page 11

Advertising
background image

Document 2.4.95, Revision 0

May, 2013

11

Fluid-Filled Overhead Distribution Transformers

Pre-Energization Inspection and Tests

After the transformer has been installed, but be-

fore it is energized, the following tests and checks

should be performed at a minimum to ensure that

the transformer is ready to be energized. The trans-

former should not be energized without successfully
completing these tests and checks.

!

DANGER

FAILURE TO FOLLOW THE INSTRUCTIONS

BELOW WILL RESULT IN DEATH OR SERIOUS

PERSONAL INJURY, AND COULD ALSO RESULT

IN DAMAGE TO THE EQUIPMENT

.

Be aware of dangerous voltages and avoid

personal contact with live terminals.

!

WARNING

FAILURE TO FOLLOW THE INSTRUCTIONS

BELOW COULD RESULT IN DEATH OR SERIOUS

PERSONAL INJURY, AND COULD ALSO RESULT

IN DAMAGE TO THE EQUIPMENT.
• Only qualified personnel with appropriate

equipment should measure transformer

voltages.

• Wear personal protective equipment (PPE)

to prevent injury from potential arc-flash or

contact with dangerous voltages.

• Make sure the transformer is securely and

effectively grounded at all times.

• Current transformer (CT) leads, if present,

must be connected to a metering load or

shorted together and grounded to prevent

dangerous voltages at the CT terminals.

• After successful completion of the

recommended tests and checks, energize the

transformer from a remote location.

1. Ratio Test—Using a transformer turns ratio tester

(TTR), perform a ratio test to verify the primary-

to-secondary winding ratio. The measured

value should be within 0.5% of the voltage ratio

indicated on the transformer nameplate. If the

transformer is provided with high-voltage taps

(or low-voltage taps on step-up/step-down trans-

formers having low-voltage ratings above 600

Volts), measure the ratio at each tap position to

ensure that each of the ratios is correct.

When internal low-voltage windings have been

reconfigured by the user as described above in

“Reconfiguring the Low-Voltage Internal Con-

nections”, the ratio test will confirm that the

transformer has the correct output voltage and

polarity. Follow the instructions and safety pre-

cautions provided by the TTR equipment manu-

facturer. For additional information about ratio

testing, refer to IEEE Standard C57.12.90.

2. Insulation Resistance Test—Perform a 1,000-

Volt insulation test (Megger test) to measure the

resistance of the insulation between windings

and from each winding to ground. Follow the

instructions and safety precautions provided

by the test equipment manufacturer. Prior to

the test, bushings must be thoroughly cleaned

with denatured alcohol to remove any moisture

or contaminants that could influence the test

results. Measured resistance should be at least

1.0 GΩ.

3. Multiple-Voltage Switch Setting—On transform-

ers provided with a multiple-voltage switch,

check the switch setting to make sure it is set

to the correct position and that the locking

screw, if provided, is engaged. When specified,

the multiple-voltage switch may be mounted

internally and accessibly only after removing the

transformer cover or, if provided, the handhole

cover. Before removing the cover or handhole

cover, refer to “Opening the Transformer Tank”

for instructions.

4. Tap Switch Setting—On transformers provided

with taps, check the tap switch setting to ensure

it is set to the proper position for the required

voltage, and that the locking screw, if provided,

is engaged. When specified, the tap switch may

be mounted internally and accessible only after

removing the transformer cover or, if provided,

the handhole cover. For transformers provided

with both taps and multiple-voltage windings,

make sure the tap switch is in the position

indicated on the nameplate when the multiple-

SECTION 4: INSPECTION AND TESTING

Advertising